Engineering changes are a primary reason mixed model material systems drift into chaos, so they must be managed as a formal change-control process, not an informal “we’ll handle it” activity. The key is synchronization: the cut-in date for the new part must align with purchasing, receiving, labeling, point-of-use presentation, and kanban authorization. PFEP should be updated before the change is released, including packaging, container quantity, locations, and replenishment triggers. During transitions, plan for controlled overlap: dual locations or dual kanban loops may be needed briefly to avoid stockouts, but they must have a clear start and end date. Old inventory requires a disposition plan to prevent ghost stock from lingering at the line. A short training moment for handlers and operators prevents wrong-part picks when the change goes live.